What projects have you seen with the biggest cost overruns (i.e. original projected cost vs the actual final cost)?

I can think of a couple:

1) Sydney Opera House: projected cost: $7 million; actual cost: $102 million.
2) Montreal Olympic Stadium: projected cost: $71 million; actual cost: $1.4 billion.
3) Denver Airport: projected cost: $2.8 billion; actual cost: $4.8 billion.

(these numbers come from various sources; your mileage may vary).
  #2  
Old 05-21-2020, 07:14 AM
mcgato is offline
Guest
 
Join Date: Aug 2010
Location: Hoboken
Posts: 1,416
Boston Big Dig: projected cost: $2.8 billion; actual cost: $8.08 billion (also 9 years behind schedule)
  #3  
Old 05-21-2020, 07:39 AM
Hermitian's Avatar
Hermitian is offline
Guest
 
Join Date: Jan 2004
Posts: 2,825
The James Webb Space Telescope: From Wikipedia: "The telescope was originally estimated to cost $1.6 billion, but the cost estimate grew throughout the early development and had reached about $5 billion by the time the mission was formally confirmed for construction start in 2008. By October 2019, the estimated cost of the project had reached $10 billion for launch in 2021."
  #4  
Old 05-21-2020, 07:46 AM
lobotomyboy63 is offline
Guest
 
Join Date: Feb 2008
Location: Secret World
Posts: 4,267
Face mask sanitizers that will allow them to be used twenty times:

"...at $60 million for 60 machines on April 3, the price was right.

But over just a few days, the potential cost to taxpayers exploded to $413 million, according to notes of a coronavirus task force meeting obtained by NBC News. By May 1, the Pentagon pegged the ceiling at $600 million in a justification for awarding the deal without an open bidding process or an actual contract. "

https://news.yahoo.com/white-house-p...154700476.html

"Even worse, scientists and nurses say the recycled masks treated by these machines begin to degrade after two or three treatments, not 20, and the company says its own recent field testing has only confirmed the integrity of the masks for four cycles of use and decontamination."
  #5  
Old 05-21-2020, 11:24 AM
wguy123 is offline
Guest
 
Join Date: Apr 2007
Posts: 2,363
$223 Million cost overrun for the tunnel to replace 99 through Seattle:

https://en.wikipedia.org/wiki/State_Route_99_Tunnel

Bad Bertha!

Another $4.5 Billion had to be added to the Hanford vitrification plant cost (over $16B total cost):

https://www.tri-cityherald.com/news/...121354623.html

Was supposed to open in 2018 and now it's pushed back to 2023.
  #6  
Old 05-21-2020, 11:52 AM
Keeve is offline
Guest
 
Join Date: Aug 2000
Location: NY/NJ, USA
Posts: 5,212
New York City's Second Avenue Subway:

According to Wikipedia: "On September 15, 1929, the Board of Transportation of the City of New York (BOT) tentatively approved the expansion, which included a Second Avenue Line with a projected construction cost of $98.9 million."

The beginning of that article says that when the project is finally complete, some time perhaps ten years from now, it will have "cost more than $17 billion." - almost 172 times the original estimate.
  #7  
Old 05-21-2020, 12:23 PM
am77494 is offline
Guest
 
Join Date: Mar 2012
Posts: 2,125
Shell (Oil Company) built the Pearl GTL (converting natural gas to oil) in Qatar. From an initial cost estimate of $5Billion , it went up to about $25 Billion.

In 2003, the project cost was estimated to be US$5 billion. However, after facing huge cost escalation, it was reported to be $18 billion in 2007,[1] and, according to Qatar Petroleum sources, final project cost is expected to reach as high as $24 billion.[9] Because Shell's contract provided them with the input gas for free, the project was calculated to be viable once the price of oil exceeded $40 per barrel.

https://en.m.wikipedia.org/wiki/Pearl_GTL
  #8  
Old 05-21-2020, 12:24 PM
Snarky_Kong is offline
Guest
 
Join Date: Oct 2004
Posts: 8,610
Quote:
Originally Posted by Keeve View Post
New York City's Second Avenue Subway:

According to Wikipedia: "On September 15, 1929, the Board of Transportation of the City of New York (BOT) tentatively approved the expansion, which included a Second Avenue Line with a projected construction cost of $98.9 million."

The beginning of that article says that when the project is finally complete, some time perhaps ten years from now, it will have "cost more than $17 billion." - almost 172 times the original estimate.
$98.9M is $1.4B in 2020 dollars. That cost overrun calculation is more complicated given the extreme time. Also, has the scope changed? Not quite the same if the project doubles in size vs you get the original scope for twice the price.
  #9  
Old 05-21-2020, 12:35 PM
mhendo is offline
Guest
 
Join Date: Aug 2001
Posts: 25,726
Not as high in percentage terms as some of the others here, but in terms of sheer dollars the California high speed rail link between Los Angeles and San Francisco is a contender.

Projected costs under the original estimate in 2008 were $33.6 billion, and when voters approved the plan later that year it was at $40 billion. The plan in 2016 estimated costs at $64 billion, and that's now up over $80 billion, with the opening of the full line pushed back to 2033. Some estimates now suggest that, if it's ever actually finished, it will cost close to $100 billion.
  #10  
Old 05-21-2020, 02:07 PM
yearofglad is offline
Guest
 
Join Date: Jun 2004
Posts: 478
Quote:
Originally Posted by wguy123 View Post
$223 Million cost overrun for the tunnel to replace 99 through Seattle:

https://en.wikipedia.org/wiki/State_Route_99_Tunnel
While still a cost overrun, I suppose, the Washington Department of Transportation successfully sued the contractor in charge of Big Bertha, claiming that the contractor was responsible for the breakdown, and was awarded $57.2 million.

So, still more than a $150M cost overrun out of the state's coffers.
  #11  
Old 05-22-2020, 07:28 AM
penultima thule is offline
Guest
 
Join Date: Apr 2009
Location: Sydney, Australia
Posts: 3,510
“Boss” Tweed’s courthouse would need to be considered a candidate.
https://en.m.wikipedia.org/wiki/Tweed_Courthouse
  #12  
Old 05-22-2020, 04:07 PM
Elendil's Heir is offline
SDSAB
 
Join Date: Jun 2004
Location: 221B Baker St.
Posts: 90,114
Project Apollo initial cost projections were $7-12 billion for the whole shebang; it ended up costing over $25 billion (and still worth every penny, dammit!): https://en.wikipedia.org/wiki/Apollo_program#Costs

Costs for the B-2 Spirit bomber program rose so dramatically that each plane ended up costing over $1 billion. You could literally have made each plane out of solid gold and it would still have been cheaper (although, of course, not quite as flightworthy): https://en.wikipedia.org/wiki/Northr...nd_procurement

The Superconducting Super Collider was cancelled after about $2 billion had already been spent but when cost projections rose from $4 billion to over $12 billion. It would surely have cost a good bit more had it actually been completed: https://en.wikipedia.org/wiki/Superc...Super_Collider

Space Shuttle costs ended up being much higher than initially projected: "When all design and maintenance costs are taken into account, the final cost of the Space Shuttle program, averaged over all missions and adjusted for inflation, was estimated to come out to $1.5 billion per launch, or $60,000/kg (approximately $27,000 per pound) to LEO. This should be contrasted with the originally envisioned costs of $118 per pound of payload in 1972 dollars (approximately $635 per pound adjusting for inflation to 2011)." From here: https://en.wikipedia.org/wiki/Critic...huttle_program
  #13  
Old 05-22-2020, 04:21 PM
RealityChuck's Avatar
RealityChuck is offline
Charter Member
 
Join Date: Apr 1999
Location: Schenectady, NY, USA
Posts: 43,545
The NYS Capitol Buiding took over 30 years to complete and a final cost of $25 million in 1899 ($768 million today). I can't see the original cost, but on a percentage basis, it has to be up there. There were three architects and two different architectural styles, and people would run for governor promising to finish it. The "million dollar staircase" is so named because it supposedly cost a million dollars, which was real money at the time.
__________________
"If a person saying he was something was all there was to it, this country'd be full of rich men and good-looking women. Too bad it isn't that easy.... In short, when someone else says you're a writer, that's when you're a writer... not before."
Purveyor of fine science fiction since 1982.
  #14  
Old 05-22-2020, 04:44 PM
Siam Sam is offline
Elephant Whisperer
 
Join Date: Nov 2006
Location: Honolulu, Hawaii
Posts: 42,030
I don't have the figures handy, but Bangkok's Skytrain (aboveground rapid transit) and later its subway both were decried for cost overruns. As has Honolulu's aboveground mass-transit project, yet to be finished. I guess this is common in projects like these.
__________________
"Hell is other people." -- Jean-Paul Sartre
  #15  
Old 05-22-2020, 05:13 PM
Noelq is offline
Charter Member
 
Join Date: Nov 2000
Location: Sacramento, CA
Posts: 988
California High Speed Rail.

Bond passed for 9 billion to complete.

Currently, its projected to cost $68.8 billion. And growing.
  #16  
Old 05-22-2020, 06:02 PM
Colibri's Avatar
Colibri is offline
SD Curator of Critters
Moderator
 
Join Date: Oct 2000
Location: Panama
Posts: 45,515
It's sometimes been said that the Panama Canal was the last US government project that was brought in ahead of schedule and under budget.
  #17  
Old 05-22-2020, 06:44 PM
dalej42 is offline
Charter Member
 
Join Date: Feb 2004
Location: Chicago
Posts: 16,469
Surely the new Berlin airport would be a contender?
__________________
Twitter:@Stardales IG:@Dalej42 He/Him/His
  #18  
Old 05-22-2020, 06:46 PM
turtlescanfly is offline
Guest
 
Join Date: May 2013
Location: Southeastern Pennsylvania
Posts: 442
Every trip to Costco I've ever made.

Sent from my SM-G955U1 using Tapatalk
  #19  
Old 05-22-2020, 07:54 PM
pkbites's Avatar
pkbites is offline
Charter Member
 
Join Date: Apr 2000
Location: Majikal Land O' Cheeze!
Posts: 11,265
Quote:
Originally Posted by Mark Finn View Post
3) Denver Airport: projected cost: $2.8 billion; actual cost: $4.8 billion.

THAT piece of shit cost 4.8 BILLION?
  #20  
Old 05-22-2020, 08:19 PM
penultima thule is offline
Guest
 
Join Date: Apr 2009
Location: Sydney, Australia
Posts: 3,510
Some of the grand Gothic projects of the medieval period might have really stretched their original budget.
York Minster Cathedral
Construction began in 1220 and ended in 1472, 252 years to complete

The cornerstone for Cologne Cathedral was laid in 1248, and construction pace progressively slowed until 1473 when it stopped into the 1840s and finished in 1880 — 632 years.

Last edited by penultima thule; 05-22-2020 at 08:20 PM.
  #21  
Old 05-22-2020, 08:40 PM
Xema is offline
Guest
 
Join Date: Mar 2002
Posts: 12,571
Quote:
Originally Posted by Noelq View Post
California High Speed Rail.

Bond passed for 9 billion to complete.

Currently, its projected to cost $68.8 billion. And growing.
While the original San Francisco to Los Angeles scheme has shriveled to Merced to Bakersfield, representing about 22% of the originally planned distance and perhaps 5% of the potential ridership.
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is Off
HTML code is Off

Forum Jump


All times are GMT -5. The time now is 06:31 AM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2020, vBulletin Solutions, Inc.

Send questions for Cecil Adams to: cecil@straightdope.com

Send comments about this website to: webmaster@straightdope.com

Terms of Use / Privacy Policy

Advertise on the Straight Dope!
(Your direct line to thousands of the smartest, hippest people on the planet, plus a few total dipsticks.)

Copyright 2019 STM Reader, LLC.

 
Copyright © 2017